FIDIC 2017 · FIDIC 13.3.1

detailed particulars

The Contractor's priced proposal for an instructed Variation, with its effect on the Programme. It is due within 28 days of the instruction.

On the Aldermere project

Merrow Vale's detailed particulars for Variation 1, received on 23 June 2026, sought GBP 198,000 and EOT 21 days.