NEC4 · ECC 62.6

deemed acceptance

Acceptance the contract treats as given after a Project Manager's silence. The Contractor must first notify the failure to reply, and a further period must pass.

On the Aldermere project

Merrow Vale's resubmitted programme had no reply. After the failure was notified on 25 February, it was treated as accepted on 4 March 2026.

Also written as

  • treated as accepted
  • treated as acceptance
  • deemed accepted