FIDIC 2017 · FIDIC 8.3(g)
critical path
The chain of linked activities with no float, so delay to any of them delays completion. A Red Book programme must show it.
On the Aldermere project
Dana gave a Notice on 30 January 2026 that the first programme did not comply: it showed no float or critical path.
Also written as
- critical paths
Where you meet it
- Module 2: Starting out and the programmeNEC4 vs FIDIC 2017