NEC4 · ECC Option C 54.1 (Option D 54.5)
Contractor's share
Under Options C and D, the Contractor's part of any saving or overrun against the target. It is assessed at Completion and again in the final assessment.
On the Aldermere project
The final saving of GBP 272,000 fell in the 90% to 110% range, so Merrow Vale's share was GBP 136,000.