Claim
One Party's request to the other for something it says the contract entitles it to, such as more time or money. Either Party can claim.
“a request or assertion by one Party to the other Party for an entitlement” (FIDIC 1.1.6)
On the Aldermere project
Claim 1 is Merrow Vale's Red Book Claim for the buried concrete, settled at EOT 7 days and GBP 76,500.