NEC4 · ECC X22.1(2)

Budget

Under Option X22, the items and amounts in the Contract Data that form the project budget. If the final Project Cost is lower, the Contractor earns the budget incentive.

The contract's words

“the items and amounts stated in the Contract Data” (X22.1(2))

Also written as

  • Project Cost
  • budget incentive