NEC4 · ECC 50.2
application for payment
The Contractor's statement, sent before an assessment date, of the amount it considers due. Without one, the amount due cannot rise above the previous amount due.
On the Aldermere project
Merrow Vale's 30 June 2026 application was late, so the 29 June amount due was capped and that payment was nil.
Also written as
- applications for payment
Where you meet it
- Module 10: PaymentPractitioner Course
- Module 2: Assessment dates, applications and certificatesPayment and Defined Cost