FIDIC 2017 · FIDIC 8.4
advance warning
A Red Book warning, from a Party or the Engineer, of likely future events that could delay the work or raise the Contract Price. It protects no right alone.
On the Aldermere project
On 3 March 2026 Owen gave an advance warning about the buried concrete under Sub-Clause 8.4.
Where you meet it
- Module 4: Early warning and advance warningNEC4 vs FIDIC 2017