NEC4 · ECC 11.2(1)
Accepted Programme
The programme the Project Manager last accepted, or the one named in the Contract Data until then. Each accepted programme replaces the one before it.
“the latest programme accepted by the Project Manager” (11.2(1))
On the Aldermere project
Merrow Vale's resubmitted programme was treated as accepted on 4 March 2026. It became the Accepted Programme used for CE007.